User Guide

How-To Tutorials

Capacity Planning

How to Run a Capacity Check

  1. Go to Capacity Planner & Insights → Analytics Dashboard
  2. Click Scope → select a Project and Date Range → click Apply
  3. Review:
    • Team Allocation tab - who has what and how much
    • Assignee Capacity tab - per-person load vs. estimates
    • Deadlines & Risks tab - overdue and at-risk issues
    • Status Aging tab - issues stuck in a status too long

How to Create and Save a Capacity Plan

  1. Go to Capacity Planner & Insights → Planner
  2. Click Create New Planner
  3. Select groups or teams to include, set date range and view mode
  4. Review the capacity distribution
  5. Click Save and give the plan a name
  6. Reload it anytime from the same Planner landing page

Time Tracking

How to Log Time

  1. Open the app → Time Tracking module
  2. Click Log Time button (top-right of any report or calendar)
  3. Search for the Jira issue you worked on
  4. Enter hours (e.g., 2h 30m)
  5. Select the date
  6. Optionally select an Account and Time Category
  7. Click Save

Tip: Use My Calendar to see which days have no logged time and fill in gaps quickly.


How to Review Your Daily Time (My Calendar)

  1. Open Time-Tracking & Reporting → My Work → My Calendar tab
  2. Each day cell shows total hours logged
  3. Click any day cell to see the breakdown of issues logged that day
  4. Click a cell to add, edit, or delete worklogs for that date

How to Build a Timesheet Report

  1. Go to Time-Tracking & Reporting → Reports
  2. Click Create New Report
  3. Choose a report source: Custom Filters, a Jira Saved Filter, or JQL Search
  4. Click Add Filter to set: Projects, Users/Groups/Teams, Accounts, Date Range
  5. Add Group By dimensions (up to 5, e.g., Project → Issue)
  6. Choose View Mode: Overview or Days
  7. Click Save to preserve the report configuration
  8. Click Export to download as PDF or Excel (CSV export was removed)

How to Create a Billing Account

  1. Open Time-Tracking & Reporting → Accounts
  2. Click Create Account
  3. Enter Account Name and optional Account Key
  4. Click Save
  5. Select this account from the Log Time form when logging time for that client

Portfolio Management

How to Create a Portfolio

  1. Go to Portfolio Management in the module switcher Step 1

  2. Click Filter → choose Manual Filter or Saved Filter or JQL Step 2

  3. Set your scope (projects, issue types, date range) Step 3

  4. Click Apply to preview matching issues Step 4

  5. Click Save


How to Switch Portfolio Views

With a portfolio open, use the view mode selector (top-right) to switch between: Table → Gantt Chart → Graph View → Treemap → Pie Chart → Board View

Views

How to Edit Dates in the Gantt Chart

  1. Open a portfolio → switch to Gantt Chart view
  2. Drag the left edge of a bar to change the start date
  3. Drag the right edge to change the due date
  4. Changes save directly to the Jira issue's Start Date and Due Date fields

Gantt1

How to Create a Gantt Dependency

  1. Open portfolio in Gantt Chart view
  2. Hover over a task bar's end point until the connector dot appears
  3. Drag to the start of the dependent task
  4. Dependency types: Finish-to-Start (FS), Start-to-Start (SS), Finish-to-Finish (FF), Start-to-Finish (SF)

Gantt2

Backlog Prioritization

How to Score a Backlog

  1. Go to Backlog Prioritization → Backlog Table
  2. Select your Jira project
  3. Choose a scoring template (e.g., ICE, RICE, WSJF)
  4. Click any metric cell to enter values inline
  5. The Score column calculates automatically
  6. Click Save Report to preserve the scored snapshot

How to Use the Priority Matrix

  1. Score your backlog using the steps above
  2. Click the Matrix view button (top-right view switcher)
  3. Each dot represents one issue
  4. Hover on a dot to see issue details
  5. Click Matrix Settings to change the X and Y axes

How to Create a Custom Scoring Template

  1. Open the template selector → Manage Templates → Create New Template
  2. Enter Template Name
  3. Add each metric (name, input type, range)
  4. Enter the formula referencing your metric names (e.g., Impact * Confidence * Ease)
  5. Click Save - the template appears in the template selector

Admin Tasks

How to Grant Access with a Permission Role

  1. Go to Settings → Data Access → Permission Roles
  2. Create or select a role, and choose its permission set and scope (global, program, or specific teams)
  3. Search for the user by name or email and assign the role
  4. Click Save - takes effect immediately

RBAC


How to Create a Team

  1. Open Time-Tracking & Reporting or Capacity Planner & Insights module
  2. Click Team Management in the sidebar
  3. Click Create Team
  4. Enter Team Name and add members by search
  5. Click Save

RBAC