Release Burndown & Burnup

Data & Series

Data Tab

Data tab

SettingWhat It DoesDefault
Include sub-tasksIncludes sub-tasks alongside their parent items, with their own estimate, in every calculationOff
Track scope by 'Fix versions' (BETA)Limits the release scope to work items whose Fix versions match the versions you pick. All other work items from the data source are left outOff
Intervals ofThe time interval each point on the chart covers: 1 day, 1 week, 2 weeks, 3 weeks, 4 weeks, 6 weeks, 8 weeks, or 1 calendar month. Match it to your sprint length if you work in sprints1 week
Calculate byWhat every calculation measuresStory Points

Fix versions

Fix versions picker

When Track scope by 'Fix versions' (BETA) is on, a Fix versions list appears. Open it to see fix versions from Jira, or type to search, then tick as many as you need. To add a version that is not listed, type its name and press Enter, or click Add "..." at the bottom of the list.

Calculate by

Calculate by options

OptionMeasures
Story PointsSum of story points
Story Point EstimateSum of the team-managed story point estimate field
Original Time Estimate (hours)Sum of original estimates
Time Remaining & Time Spent (hours)Remaining estimate and time spent
Work Item CountNumber of work items
Custom numeric field...Sum of a custom numeric field you pick under Numeric field

If Custom numeric field... is chosen but no field is picked, the gadget asks you to complete the setting before it draws the chart.

Series Tab

Series to Display

Series to Display

SeriesShowsDefault
Ideal BurndownThe ideal remaining-work line from release start to end, based on ScopeOn
Ideal BurnupThe ideal done-work line from release start to end, based on ScopeOn
RemainingTotal remaining work at each point in timeOn
BurnedTotal work done at each point in timeOn
ScopeTotal work to be done at each point in time - shows scope changesOn
Forecast ScopeDashed line predicting the scope, from the end of the Scope line to the release end dateOff
Forecast BurndownDashed line from the start of the release to the estimated end dateOff
Forecast RemainingDashed line from the end of the Remaining line to the estimated end dateOff
Forecast BurnedDashed line from the end of the Burned line to the estimated end dateOff

For a classic burndown chart, select only Ideal Burndown and Remaining. For a classic burnup chart, select only Ideal Burnup and Burned. The forecast lines are calculated on the Forecast tab.

Calculate the ideal series based on

Calculate the ideal series based on

OptionThe Ideal Lines Start From
The current scope (default)The current (latest) Scope
The initial scopeScope at the start of the release
A fixed scope value ofA number you type - useful when you know the rough total but have not added all the work items or estimates to Jira yet

With Intervals of set to 1 day, the ideal lines stay flat on Saturdays and Sundays.